Hello,
At 05:23 06-03-2015, For and on Behalf of CEO <ceo at afrinic.net> wrote:
>The internal systems and processes have been reviewed
>and appropriate measures taken such as more stringent monitoring,
>regular system audit, redundancy, etc to avoid this in the future.
There was a failure of the internal monitoring system as it did not
catch the problem. According to the above appropriate measures have
been taken such as more stringent monitoring. It looks like the
existing monitoring is not strict or precise if the internal
monitoring system failed. The paragraph about how a similar incident
will be avoided in future is not very convincing.
Is it the view of AfriNIC that its RPKI system is critical infrastructure?